Hongjing EVA project
Lianyungang, Jiangsu
Publicly reported project information for three tubular EVA lines in Xuwei New District.
Project milestones with dates
The status below reflects public information released by the Lianyungang Municipal Science and Technology Bureau on 18 March 2025.
It is presented with dates so visitors can distinguish reported milestones from current operating claims.
Project construction started
Construction began for the Shenghong chemical new-materials project in Xuwei New District.
First EVA line entered production
The first 200,000-tonne-per-year tubular EVA unit was reported in production.
Second line trial-production milestone
The second EVA unit was reported as entering trial production by the end of March.
Third line in final installation
The third EVA unit was reported at the installation-finishing stage.
What sits behind an EVA supply discussion
Manufacturing scale is only one part of product qualification. Supply, process and technical documentation must be considered together.
Tubular process platform
The disclosed project is based on three tubular EVA lines, each planned at 200,000 tonnes per year.
Integrated site context
The project is located within the Lianyungang petrochemical industry base and Shenghong industrial system.
Grade release information
Purchasing and qualification should reference current specifications, TDS documents and agreed release criteria.
Application qualification
Customers should test candidate grades under their own formulation, equipment and end-use conditions.
High-end copolymer work beyond EVA
In April 2026, Shenghong reported that Hongjing had completed EBA trial research and was advancing a 50,000-tonne-per-year high-end copolymer facility that includes EBA.
The disclosed research focus is ethylene-acrylate copolymer for semi-conductive shielding materials used in high-voltage cable systems.